Hmm, that's not really what I envision as 'redundant' :-/ Is there an overview somewhere how this has been sorted for the other datacenters Linode uses? Are they better equipped? --
On 31 May 2015, at 16:09, Alex Forster via Outages <outages@outages.org> wrote:
The redundancy was grid + generator. Unfortunately both failed.
<signature-logo.png> Alex Forster Network Engineer | Linode From: Scott Howard via Outages <outages@outages.org> Sent: Sunday, May 31, 2015 4:37AM To: Frank Bulk <frnkblk@iname.com> Cc: Outages Mailing List <outages@outages.org> Subject: Re: [outages] Linode Fremont outage
On Sat, May 30, 2015 at 8:04 PM, Frank Bulk via Outages <outages@outages.org> wrote: Are suites tied to just one generator?
Unless things have changed since I was last there, yes. HE do not offer redundant power (at least, not at FMT2).
HE offer a great price point, but as the saying goes, you get what you pay for!
Scott
_______________________________________________ Outages mailing list
Outages@outages.org https://puck.nether.net/mailman/listinfo/outages