Are suites tied to just one generator? Frank From: Outages [mailto:outages-bounces@outages.org] On Behalf Of Walt Wollny via Outages Sent: Saturday, May 30, 2015 9:50 PM To: Alex Rubenstein Cc: outages@outages.org Subject: Re: [outages] Linode Fremont outage Here it is right from HE You can always call us. Sorry I did not see this sooner Walt At the Fremont 2 facility at 48233 Warm Springs Blvd, Fremont CA <x-apple-data-detectors://0> on May 29th at approximately 6:30 PM PST <x-apple-data-detectors://2> PG&E (the power utility) had an outage. Generators 1,2,4,5,6,7,8 started correctly and transferred. Customers in suites 1100,1200,1400,1500 experienced no issues. Generator 3 experienced an electromechanical failure. We are in the process of remediating this. Customers in suite 1300 are currently affected. The estimate time to restoration is 9:30 PM <x-apple-data-detectors://3> . We apologize for the inconvenience. Sent from my iPhone On May 30, 2015, at 5:39 PM, Alex Rubenstein via Outages <outages@outages.org <mailto:outages@outages.org> > wrote: So the outage was OK to have since they had staff on site? On May 30, 2015 09:01, Paul WALL via Outages <outages@outages.org <mailto:outages@outages.org> > wrote: It's a good thing Hurricane Electric had electricians on site to deal with the outage. If it were an Equinix or Telx site, the response would have assuredly been far worse. Paul _______________________________________________ Outages mailing list Outages@outages.org <mailto:Outages@outages.org> https://puck.nether.net/mailman/listinfo/outages _______________________________________________ Outages mailing list Outages@outages.org <mailto:Outages@outages.org> https://puck.nether.net/mailman/listinfo/outages